You guys asked me to keep you up to date on my Garage so here goes.
For masons, I have been paying the guys that work for the neighbor to work on Saturdays.
First it kept raining and we could not get into the hole to work. (even had a 10 yard cement truck buried to its axles)
then one day it stopped raining (back in June) and turned 98 deg every day, and I could not get anybody to show up to work on weekends. Finally things are moving again. Only about 20 more block to go!
Next week they pore concrete into the pilasters, then I can order steel! , pore the top floor then build the wood frame top garage!
Pictures will be coming quicker once the block work is done, I hope
http://mywpages.comcast.net/towpro/garage.htm
For masons, I have been paying the guys that work for the neighbor to work on Saturdays.
First it kept raining and we could not get into the hole to work. (even had a 10 yard cement truck buried to its axles)
then one day it stopped raining (back in June) and turned 98 deg every day, and I could not get anybody to show up to work on weekends. Finally things are moving again. Only about 20 more block to go!
Next week they pore concrete into the pilasters, then I can order steel! , pore the top floor then build the wood frame top garage!
Pictures will be coming quicker once the block work is done, I hope
http://mywpages.comcast.net/towpro/garage.htm